Athens TransparencyPublic records. Clearer understanding.Local research preview

Project histories

Market Park improvements: the documented record

Follow a reported project-account actual, budget stages, an advisory electrical recommendation, and Council approval of Phase 1 of the Market Park master plan. The record is limited to Market Park and excludes similarly named Athens Marketplace records and routine event-use approvals.

Approvals, contract amounts, and reported expenditure describe different stages. They are not added together as a project total.

  1. FY2023 Market Park Improvements project-account actualReported project-account spending

    The Capital Improvement Fund history reports $38,010 of FY2022-23 audited spending in account 08-0801-6084, Market Park Improvements. This is an annual project-account actual; the source does not identify vendors, invoices, or the work purchased, and it is not added to later budget authority as a project total.

    Amount reported at this stage: $38,010

    Search the archive: 08-0801-6084 · Market Park Improvements

  2. FY2026 budget provides $250,000 for Market Park improvementsBudgeted and amended funding

    The later FY2026-27 budget comparison reports $250,000 as the FY2025-26 budgeted and amended amount for account 08-0801-6084, Market Park Improvements. The corresponding budget priority describes paving, resurfacing, and pedestrian-safety improvements, with $10,000 for plans and specifications and $240,000 for construction. Budget authority is not expenditure or a construction award.

    Amount reported at this stage: $250,000

    Search the archive: 08-0801-6084 · Market Park Improvements · $250,000

  3. Recreation board recommends electrical improvementsAdvisory recommendation · PASSED

    The Recreation Advisory Board recommended that City Council purchase new electrical equipment and proceed with electrical improvements at Market Park. This advisory action does not authorize a city contract or expenditure.

    • Ron Starr: yes
    • Johnny Coffman: yes
    • Mary Scudder: yes
    • Linda Long: yes
    • Moises Contreras: yes
    • Bob Miller: yes
    • Larry Rhodes: absent

    Recorded vote: Recommend Market Park electrical improvements

    Reviewed decisions: View decision

    Search the archive: Market Park electrical improvements

  4. Council approves Phase 1 of Market Park master planPhase approval · PASSED

    Council approved Phase 1 of the Market Park master plan presented by Kimley-Horn under an engineering-agreement agenda item. The reviewed minutes do not state the agreement amount, detailed Phase 1 scope, contract schedule, or completion status.

    • Curtis: yes
    • Duggan: yes
    • Eaton: yes
    • Sherlin: yes

    Recorded vote: Approve Phase 1 of the Market Park master plan

    Reviewed decisions: View decision

    Search the archive: Market Park Master Plan · Phase 1 · Kimley Horn

  5. FY2027 manager proposes $1.5 million for Market Park improvementsManager-proposed funding

    The FY2026-27 budget comparison lists a $1.5 million manager-proposed amount for Market Park Improvements. The budget priority describes completing the master plan and Phase I work involving underground electrical improvements, site lighting, and parking-area resurfacing, with later sidewalks and landscaping identified as Phase II. The reviewed table leaves the council-approved column blank, so this is not presented as approved funding.

    Amount reported at this stage: $1,500,000

    Search the archive: Market Park Improvements · $1,500,000 · Phase I · Phase II

What remains unconnectedEvidence needed to complete the trail.
  • The FY2023 project-account actual does not identify vendors, invoices, or completed work.
  • The $250,000 FY2025-26 budgeted and amended amount is funding authority, not proof of award, expenditure, or completion.
  • The November 2025 minutes approve Phase 1 but do not state the engineering-agreement amount or detailed scope.
  • The $1.5 million FY2026-27 figure is manager-proposed; the reviewed comparison does not show a council-approved amount.
  • No reviewed source reconciles appropriations, contracts, change orders, invoices, payments, or final project cost.
  • No reviewed source confirms completion of Phase 1 or later sidewalks and landscaping.
  • The January and July 2024 consent agendas mention Market Park event scheduling or pavilion use; those operational event approvals are excluded because they do not authorize capital improvements.
  • Athens Marketplace records were excluded as a different subject.

Related department spending history · Records review · Search related source records