Athens TransparencyPublic records. Clearer understanding.Local research preview

Check the scanned record

Compare the original on the left with machine-read text on the right. Start with the first three examples, then continue through the sample.

Your first review is saved below. Proposed revisions remain unverified. Tell us the item number and any further corrections; this page does not submit new decisions.
PreviousNext

Item 14 of 46 · PDF page 28

2023-07-18-City-Council-Meeting-Packet.pdf · 2023

Check names, dates, amounts, votes, and reading order. Blank pages and diagrams may legitimately have little searchable text.

Saved review: No specific feedback recorded · No explicit feedback for this item; the financial-table observation was corrected to item 15.

Original scanned page

Open original in a larger view

Machine-read text

Unverified · 1,637 characters

Matt -

See below for some quick take off / estimates for the Ingleside Pickleball overlay. As we
discussed yesterday, there would need to be some design decisions made regarding the
renovation. We may want to go ahead and fully remove the posts to better access and
resurface the whole court area. | included a 5% contingency on all contractor supplied items. |
didn't include shade structures (115k), but that can be added if desired and potentially
installed in house to save mark up.

best,
db

Clearing/Grubbing - AL $15,000. Typical line item that contractors use for site prep.

Clearing/grubbing/mobilization. Site prep which includes removal. Demolition is also a factor.
Prep work for making a lay down area to put all of their equipment.

Parking lot and sidewalk - $105,000. This has contingency

Removal and replacement of sidewalk (access) - 2,900 sf @ 10/sf - $29,000

Fencing (remove / replace approx. 10' perimeter) - 670 If @50/If - $33,500

LED upgrades (both tennis / pickleball) - $125,000. Lighting number from Musco from our
original pickleball numbers. If they are only replacing the light fixtures, 4° high fencing - 420 If
@ 60 / If - $25,200.

Court surfacing (asphalt and sports coating) 27,000 sf @ 6/sf - 162,000. $6/square foot is on
the high side but this is a number for contingency. This is to accommodate for any unforeseen
circumstances.

SUBTOTAL: $494,700
Mobilization (5%) - $24,735
+ $494,700 =

$519,435.00

By Owner (City of Athens)

Benches - 16 @1,500 ea. - $24,000

Nets 12 - @ $2,500 - $30,000

Windscreen - (approx) 850 If @ 20 / If - $17,000
Subtotal: $71,000

+$519,435 =

$590,435.00