Unit Price Total Cost Unit Price  Total Unit Price  Total Unit Price   Total 
105-01 CONSTRUCTION STAKES, LINES AND GRADES LS 1 $40,000.00 $40,000.00 $25,000.00 $25,000.00 $9,000.00 $9,000.00 4,550.00$        4,550.00$         
202-01.50 REMOVAL OF STRUCTURES AND OBSTRUCTIONS EACH 2 $1,500.00 $3,000.00 $2,500.00 $5,000.00 $3,500.00 $7,000.00 650.00$           1,300.00$         
202-02.21 REMOVAL OF PIPE (12" RCP) L.F. 121 $15.00 $1,815.00 $18.00 $2,178.00 $50.00 $6,050.00 65.00$             7,865.00$         
203-01 ROAD & DRAINAGE EXCAVATION (UNCLASSIFIED) C.Y. 476 $45.00 $21,420.00 $78.00 $37,128.00 $60.00 $28,560.00 45.50$             21,658.00$        
203-04 PLACING AND SPREADING TOPSOIL C.Y. 83 $45.00 $3,735.00 $60.00 $4,980.00 $40.00 $3,320.00 91.00$             7,553.00$         
203-06 WATER M.G. 3 $120.00 $360.00 $150.00 $450.00 $100.00 $300.00 1,170.00$        3,510.00$         
209-05 SEDIMENT REMOVAL C.Y. 12 $20.00 $240.00 $40.00 $480.00 $10.00 $120.00 52.00$             624.00$            
209-08.03 TEMPORARY SILT FENCE (WITHOUT BACKING) L.F. 352 $4.00 $1,408.00 $3.75 $1,320.00 $5.00 $1,760.00 4.25$               1,496.00$         
209-08.07 ROCK CHECK DAM EACH 2 $1,100.00 $2,200.00 $725.00 $1,450.00 $900.00 $1,800.00 325.00$           650.00$            
209-08.08 ENHANCED ROCK CHECK DAM EACH 2 $1,300.00 $2,600.00 $850.00 $1,700.00 $900.00 $1,800.00 650.00$           1,300.00$         
209-09.43 CURB INLET PROTECTION (TYPE 4) EACH 1 $475.00 $475.00 $500.00 $500.00 $150.00 $150.00 400.00$           400.00$            
303-01 MINERAL AGGREGATE, TYPE A BASE, GRADING D TON 434 $70.00 $30,380.00 $69.00 $29,946.00 $90.00 $39,060.00 110.50$           47,957.00$        
307-01.08 ASPHALT CONCRETE MIX (PG64-22) (BPMB-HM), GRADING BM-2 TON 138 $150.00 $20,700.00 $195.00 $26,910.00 $220.00 $30,360.00 383.50$           52,923.00$        
403-01 BITUMINOUS MATERIAL FOR TACK COAT (TC) TON 1 $1,100.00 $1,100.00 $1,404.00 $1,404.00 $1,490.00 $1,490.00 4,160.00$        4,160.00$         
411-01.10 ACS MIX (PG64-22) GRADING D TON 64 $200.00 $12,800.00 $320.00 $20,480.00 $329.00 $21,056.00 403.00$           25,792.00$        
607-02.02 15" CONCRETE PIPE CULVERT (CLASS III) L.F. 65 $180.00 $11,700.00 $145.00 $9,425.00 $210.00 $13,650.00 110.50$           7,182.50$         
611-07.01 CLASS A CONCRETE (PIPE ENDWALLS) C.Y. 3 $2,600.00 $7,800.00 $1,485.00 $4,455.00 $3,530.00 $10,590.00 5,460.00$        16,380.00$        
611-07.30 15IN ENDWALL (SIDEDRAIN) EACH 2 $4,500.00 $9,000.00 $2,500.00 $5,000.00 $4,450.00 $8,900.00 5,460.00$        10,920.00$        
701-02 CONCRETE DRIVEWAY S.F. 693 $13.00 $9,009.00 $22.00 $15,246.00 $16.00 $11,088.00 15.00$             10,395.00$        
702-01 CONCRETE CURB C.Y. 17 $1,500.00 $25,500.00 $750.00 $12,750.00 $1,200.00 $20,400.00 585.00$           9,945.00$         
707-10.08 WIRE MESH (SD-MSE-1) S.Y. 8 $150.00 $1,200.00 $175.00 $1,400.00 $65.00 $520.00 15.00$             120.00$            
709-05.05 MACHINED RIP-RAP (CLASS A-3) TON 100 $75.00 $7,500.00 $86.00 $8,600.00 $114.00 $11,400.00 104.00$           10,400.00$        
709-05.06 MACHINED RIP-RAP (CLASS A-1) TON 82 $75.00 $6,150.00 $86.00 $7,052.00 $104.00 $8,528.00 104.00$           8,528.00$         
713-02.21 SIGN POST DELINEATION ENHANCEMENT L.F. 6 $6.00 $36.00 $24.00 $144.00 $5.00 $30.00 16.00$             96.00$              
713-11.02 PERFORATED/KNOCKOUT SQUARE TUBE POST LB. 33 $6.00 $198.00 $5.50 $181.50 $5.00 $165.00 9.00$               297.00$            
713-13.02 FLAT SHEET ALUMINUM SIGNS (0.080" THICK) S.F. 7 $18.00 $126.00 $16.00 $112.00 $16.00 $112.00 25.00$             175.00$            
717-01 MOBILIZATION LS 1 $60,000.00 $60,000.00 $25,000.00 $25,000.00 $50,000.00 $50,000.00 11,050.00$      11,050.00$        
740-10.03 GEOTEXTILE (TYPE III) (EROSION CONTROL) S.Y. 275 $12.00 $3,300.00 $6.25 $1,718.75 $4.00 $1,100.00 29.00$             7,975.00$         
740-11.02 TEMPORARY SEDIMENT TUBE 12IN L.F. 430 $5.00 $2,150.00 $3.50 $1,505.00 $9.00 $3,870.00 5.20$               2,236.00$         
801-01 SEEDING (WITH MULCH) UNIT 3 $60.00 $180.00 $110.00 $330.00 $200.00 $600.00 1,950.00$        5,850.00$         
801-01.07 TEMPORARY SEEDING (WITH MULCH) UNIT 2 $50.00 $100.00 $110.00 $220.00 $50.00 $100.00 325.00$           650.00$            
801-02 SEEDING (WITHOUT MULCH) UNIT 4 $45.00 $180.00 $105.00 $420.00 $175.00 $700.00 325.00$           1,300.00$         
801-03 WATER (SEEDING & SODDING) M.G. 1 $120.00 $120.00 $150.00 $150.00 $250.00 $250.00 1,560.00$        1,560.00$         
805-12.02 EROSION CONTRL BLANKET (TYPE II) S.Y. 396 $2.00 $792.00 $4.40 $1,742.40 $4.00 $1,584.00 38.00 $             15,048.00$        
Sub Total = $287,274.00 $254,377.65 $295,413.00 $301,845.50
105-01 CONSTRUCTION STAKES, LINES AND GRADES LS 1 $15,000.00 $15,000.00 $15,000.00 $15,000.00 $9,000.00 $9,000.00 4,030.00$        4,030.00$         
202-03 REMOVAL OF RIGID PAVEMENT, SIDEWALK, ETC. S.Y. 24 $100.00 $2,400.00 $25.00 $600.00 $50.00 $1,200.00 35.10$             842.40$            
202-03.01 REMOVAL OF ASPHALT PAVEMENT S.Y. 1072 $20.00 $21,440.00 $15.00 $16,080.00 $22.00 $23,584.00 29.25$             31,356.00$        
202-08.10 REMOVAL OF CURB (CONCRETE CURB) L.F. 945 $20.00 $18,900.00 $7.00 $6,615.00 $16.00 $15,120.00 6.50$               6,142.50$         
203-07 FURNISHING & SPREADING TOPSOIL C.Y. 141 $50.00 $7,050.00 $65.00 $9,165.00 $125.00 $17,625.00 110.50$           15,580.50$        
209-05 SEDIMENT REMOVAL C.Y. 11 $20.00 $220.00 $40.00 $440.00 $10.00 $110.00 58.50$             643.50$            
209-09.43 CURB INLET PROTECTION (TYPE 4) EACH 11 $475.00 $5,225.00 $500.00 $5,500.00 $150.00 $1,650.00 325.00$           3,575.00$         
209-40.33 CATCH BASIN PROTECTION (TYPE D) EACH 1 $475.00 $475.00 $550.00 $550.00 $450.00 $450.00 1,040.00$        1,040.00$         
303-01 MINERAL AGGREGATE, TYPE A BASE, GRADING D TON 108 $60.00 $6,480.00 $69.00 $7,452.00 $100.00 $10,800.00 106.60$           11,512.80$        
307-01.08 ASPHALT CONCRETE MIX (PG64-22)(BPMB-HM) GRADING B-M2 TON 12 $180.00 $2,160.00 $836.00 $10,032.00 $581.00 $6,972.00 520.00$           6,240.00$         
403-01 BITUMINOUS MATERIAL FOR TACK COAT (TC) TON 3 $1,100.00 $3,300.00 $1,404.00 $4,212.00 $1,490.00 $4,470.00 3,120.00$        9,360.00$         
407-20.05 SAW CUTTING ASPHALT PAVEMENT L.F. 1050 $6.25 $6,562.50 $8.50 $8,925.00 $5.00 $5,250.00 5.20$               5,460.00$         
411-01.10 ACS MIX (PG64-22) GRADING D TON 484 $190.00 $91,960.00 $195.00 $94,380.00 $220.00 $106,480.00 403.00$           195,052.00$      
415-01.02 COLD PLANING BITUMINOUS PAVEMENT S.Y. 6083 $6.00 $36,498.00 $5.75 $34,977.25 $10.00 $60,830.00 2.60$               15,815.80$        
611-09.01 ADJUSTMENT OF EXISTING CATCH BASIN EACH 2 $4,500.00 $9,000.00 $3,000.00 $6,000.00 $3,430.00 $6,860.00 1,170.00$        2,340.00$         
702-01 CONCRETE CURB C.Y. 6 $1,500.00 $9,000.00 $750.00 $4,500.00 $1,130.00 $6,780.00 795.60$           4,773.60$         
709-05.05 MACHINED RIP-RAP (CLASS A-3) TON 50 $75.00 $3,750.00 $86.00 $4,300.00 $113.00 $5,650.00 110.50$           5,525.00$         
712-01 TRAFFIC CONTROL LS 1 $20,000.00 $20,000.00 $16,500.00 $16,500.00 $20,000.00 $20,000.00 5,460.00$        5,460.00$         
712-04.01 FLEXIBLE DRUMS (CHANNELIZING) EACH 69 $50.00 $3,450.00 $45.00 $3,105.00 $42.00 $2,898.00 37.05$             2,556.45$         
712-06 SIGNS (CONSTRUCTION) S.F. 135 $11.00 $1,485.00 $10.00 $1,350.00 $9.00 $1,215.00 13.50$             1,822.50$         
712-07.03 TEMPORARY BARRICADES (TYPE III) L.F. 12 $20.00 $240.00 $24.00 $288.00 $23.00 $276.00 38.00$             456.00$            
713-02.21 SIGN POST DELINEATION ENHANCEMENT L.F. 40 $6.00 $240.00 $24.00 $960.00 $4.50 $180.00 8.00$               320.00$            
713-11.01 "U" SECTION STEEL POSTS LB. 117 $6.00 $702.00 $6.00 $702.00 $5.00 $585.00 8.45$               988.65$            
 VIEW STREET ROADWAY QUANTITIES
 NORTH JACKSON ROADWAY QUANTITIES
View Street Roadway Improvements & North Jackson Street Repairs
DescriptionItem
Adams Contract, LLC
Unit Quantity
Engineer Cadence Consulting, LLCWilson Constr Group, LLC
1
16