City Of Athens Opinion of Probable Construction Cost. 5' Sidewalk 5/1/2025 
Unit Quantity Unit Cost (TOOT) Cost 
Concrete Sidewalk (4 ") SF 32610 $ 15.00 $ 489,150.00 
Concrete Driveway SF 3850 $ 20.00 $ 77,000.00 
Curb Ramp SF 880 $ 38.00 $ 33,440.00 
Curb & Gutter CY 40 $ 1,100.00 $ 44,000.00 
Earthwork/Drainage LS 1 $ 50,000.00 $ 50,000.00 
Traffic Control LS 1 $ 40,000.00 $ 40,000.00 
EPSC LS 1 $ 25,000.00 $ 25,000.00 
Retaining Wall SF 500 $ 200.00 $ 100,000 .00 
Sub Total $ 858,590.00 
20% Contingency $ 171,718 .00 
TOTAL $ 1,030,308.00 
City Of Athens Opinion of Probable Construction Cost. 10' Multi-Use Path 5/1/2025 
Unit Quantity Unit Cost (TOOT) Cost 
Concrete Sidewalk (4 ") SF 4290 $ 18.00 $ 77,220 .00 
Multi-Use Path SF 56410 $ - $ -
Base Stone TON 2333 $ 58.00 $ 135,314.00 
Binder TON 1063 $ 160.00 $ 170,080.00 
"E"Mix TON 499 $ 140.00 $ 69,860.00 
Concrete Driveway SF 7090 $ 20.00 $ 141,800 .00 
Curb Ramp SF 1045 $ 38.00 $ 39,710.00 
Curb and Gutter CY 40 $ 1,100.00 $ 44,000.00 
Earthwork/Drainage LS 1 $ 100,000.00 $ 100,000.00 
Traffic Control LS 1 $ 70,000.00 $ 70,000.00 
EPSC LS 1 $ 40,000.00 $ 40,000.00 
Retaining Wall SF 2000 $ 200.00 $ 400,000.00 
Sub Total $ 1,287,984 .00 
20% Contingency $ 257,596.80 
TOTAL $ 1,545,580.80 