Athens TransparencyPublic records. Clearer understanding.Local research preview

Source library

2023 07 18 City Council Meeting Packet

City Council · packet · 63 pages · Descriptive metadata inferred from filename

Open original PDF
Extracted text for page 24

Unverified text extraction. Check the original page for numbers, names, and layout.

PUBLIC WORKS 
Alternate #2 would upgrade the existing tennis court lighting which utilizes older technology to new LED 
light fixtures. The existing poles and wiring would remain in place with only the light fixtures to be 
replaced. The light fixtures would match those to be used on the pickleball courts and eliminate the 
facility having lighting with two different hues of lighting. We anticipate long-term savings from this work 
because the LED fixtures will reduce electricity consumption and with a 25-year warranty we would have 
little to no maintenance costs over that period. We are attempting to quantify the savings but are unsure 
if we have the data to do so and if we do, we are unsure of how quickly we will be able to calculate the 
savings. The low bid for alternate #2 is $97,630, plus the City must supply $76,632 in lighting equipment 
to be purchased through a purchasing cooperative. 
Alternate #3 includes the addition of five shade structures. However, three of these structures are 
associated with areas to be built in alternate #4. Unless at least a portion of alternate #4 is constructed, 
only two of these shades would be constructed if this alternate is accepted. These two shades would 
serve the existing tennis courts. If a small portion of additional sidewalk were constructed from alternate 
#4, then two additional shades could be constructed which would serve the pickleball courts. The fifth 
shade is intended to serve the pickleball courts which are included in alternate #4 so it would only be 
constructed if alternates #3 and #4 are accepted. The cost to construct all of alternate #3 is $112,440. 
We would have to work with the contractor to determine what the cost would be if only a portion of the 
alternate is accepted. 
Alternate #4 includes the construction of eight additional pickleball courts along with the necessary 
accessories for them. These eight courts are cheaper than the first eight courts in the base bid due to 
some economy of scale and certain components such as mobilization, fencing, grading, and lighting 
controls being constructed as part of the base bid which the courts in this alternate would utilize as well. 
The low bid for alternate #4 is $410,800, plus the City must supply $51,345 in lighting equipment to be 
purchased through a purchasing cooperative. 
Action Item 
The City Council must decide if it wishes to move forward with this project and if so which parts of the 
project it wants to construct. At a minimum, the base bid must be accepted if we choose to construct 
anything. After considering the base bid, each alternate can be evaluated independently to determine 
which, if any, of these would also be constructed. If we are to move forward with any portion of the 
contract, the portions chosen for construction need to be awarded to the low bidder with the mayor 
authorized to enter a contract with them. 
22