1 Scope of Services
Gresham Smith ("Engineer") will provide professional and technical services for the
Mayfield Dairy Stormwater Improvements project {"the Project") for the City of Athens, TN
("City" or "Owner") as described herein. Our proposed scope of services are presented in the
following paragraphs.
Engineer will provide engineering services for Owner as required to develop construction plans and
specifications for stormwater improvements as described herein.
The services generally will include the following:
Project Management & Meetings
Surveying Services
Wetlands Delineation
Permitting Applications
Preliminary Design (60%)
Final Design Deliverables (100%)
Bid Phase Services
Construction Phase Services
A general description for engineering services for the project are shown below. Detailed information
is provided in subsequent sections.
1.1 General
Provide design services for stormwater infrastructure improvements on the current Mayfield
Dairy property bounded by Oostanaula Creek, Mayfield Lane, Ingleside Avenue, and Forrest
Avenue. The Project generally includes creation of a regional detention area, sidewalks,
landscaping, and stabilization of the proposed low flow channel. A preliminary concept plan is
shown in Exhibit A.
Provide surveying services to identify and characterize existing topography, utilities, sidewalks,
curbs gutter, etc.
Prepare an Aquatic Resources Alternation Permit (ARAPJ application suitable for submittal to
Tennessee Department of Environment and Conservation (TDEC). Engineer will develop ARAP
application and supporting documentation and submit on behalf of Owner. The application fee
wil I be paid by Owner. It is assumed all improvements will qualify for coverage under the State of
Tennessee's General ARAP.
Prepare an application for coverage under TDEC General Permit for Discharges of Stormwater
Associated with Construction Activities (CGP). As part of the supporting documents for the
application, a Stormwater Pollution Prevention Plan (SW PPP) wil I be developed. Engineer will
develop GCP application and supporting documentation and submit on behalf of Owner. The
application fee will be paid by Owner.
Bid phase services as listed below.
Construction phase services as listed below.
Exclusions as listed in Section 1.10 below.