April 5, 2022  
Director Burchfield  
Page 6 of 7 
Reference: City of Athens Fire Training Facility 
  
 
for additional testing requirements should our analysis require additional information.  
 
4. Terms and Conditions will be agreed to in a mutually beneficial manner. No work can 
begin until this agreement is fully executed. 
 
5. Geotechnical investigation, report and design services are not included. 
 
6. Preparation of an Environmental Impact Statement is not included. 
 
7. Parcel boundary survey services and topography will be provided by others. 
 
8. Hazardous materials and spills investigation, testing, reporting and design are not included. 
 
9. Preparation and filing of a new subdivision map are not included. 
 
10. Completion of grant funding applications and procedures are not included. 
 
11. Wetlands delineation is not included. 
 
12. Construction phase services extending beyond sixteen (16) months from the construction 
kick-off meeting are not included. 
 
13. Development of a Storm Water Pollution Prevention Plan is included in the fee. 
 
14. Traffic studies or traffic controls design are not included. 
 
15. Permitting fees are not included. 
 
16. The client’s designated Construction Manager (Client provided) will be solely responsible  
for the Project Budget. Stantec will aid in identifying line items and quantities. 
 
17. No design is included for temporary fueling systems. 
 
18. B
orings / Site investigation to check for possible petroleum spill in soil and groundwater is 
excluded. 
 
19. Remediation related services are excluded. 
 
20. Additional landscape design beyond the minimal required by Ordinance/Regulation, 
including hardscape and a detailed landscape plan, may be provided as Additional 
Services. 
 
21. Design and permitting activities associated with wetlands, floodplains, hazardous 
materials, ecological issues, etc. are excluded from this Scope. A flood study is excluded 
from this scope. 
 
22. This scope assumes that the existing off-site drainage systems are adequate for use in this 
project. No off -site stormwater evaluation or design is included in this scope beyond 
connecting to existing drainage or utilities, or as required by the associated Stormwater 
Regulations. 