April 5, 2022  
Director Burchfield  
Page 2 of 7 
Reference: City of Athens Fire Training Facility 
  
 
plan will be submitted to the Client for review and comment. Stantec will incorporate appropriate 
responses and one revision to the concept plan is included in this scope of services.  
 
1.3 Geotechnical Services 
 
Services to be provided by Client based upon direction from Stantec as to data required.  
 
1.4 Design and Construction Documents 
 
Using the approved concept plan as a basis, Stantec will develop and provide the Client with a 
set of construction drawings for the proposed project. In the preparation of these plans, Stantec 
will provide utility coordination services with the Athens Utility Board for water, wastewater, natural 
gas, and power. Stantec will then provide Athens Utilities with preliminary construction plans for 
the purpose of utility location within the project limits. 
 
Fees for this task include one review submittal and one set of plan revisions. Additional reviews can 
be provided as an additional service. 
 
The complete construction documents, including plans and written specifications, will be 
submitted to the Client for a one-time review. Stantec will make one set of revisions following final 
Client review, if required. We anticipate the construction drawing set to consist of the following: 
 
1. Title Sheet 
2. General notes, Abbreviations and Standards 
3. Existing Conditions – based on survey provided by the Client 
4. Site Plan and Horizontal Control 
5. Grading, drainage, and storm water management 
6. Utility site plan 
7. Water and sewer lateral design from connection points within the adjacent ROW 
8. Erosion prevention and sediment control plan 
9. Construction details 
10. Fire Tower Plans (by others) 
 
1.5 Stormwater Design and Hydrology Report 
 
Stantec will design the stormwater treatment, peak runoff attenuation system, and hydrology report 
as part of the stormwater management plan.  The design of the stormwater system and its 
associated stormwater control measures (SCMs) will be based on State and local regulations.  
 
Stantec will design the stormwater infrastructure.  We will prepare and submit a hydrologic and 
hydraulic report outlining the impacts of the site on the stormwater system per Athens Stormwater 
Management Ordinance. At a minimum, this report will include the following: 
 
• Certification by Registered Engineer 
• Project Narrative 
• Existing Conditions Hydrologic Analysis 
• Post-Development Hydrologic Analysis 
• Stormwater Management System Design 
• Downstream Analysis 
31