Qty Units Unit  Price
1 LS 33,728.00 $    
1L S (4,590.00)$     
1 LS 9,689.00 $       
1 LS 1,196.15 $       
TOTAL
OH&P
Add'l Framing Mods per  structural comments 9,689.00 $                                     
40,023.15$                                   
Approved By (Architect)
Date:
Approved By (Owner)
Date:
Approved By (Contractor)
Date:
15 days
APPROVALS
‐$                                               
$15,948.60 x 7.5% 1,196.15 $                                     
Change Order No.
Integrated Properties
Allen & Hoshall
Jon Clinard
City of Athens
COR #1 through #3, COR #5 through #10 = $52,121.60. 
$52,121.60 + $38,827.00 (COR #11) = $90,948.60 total current COR cost
$90,948.60 ‐ $75,000.00 = $15,948.60 total over contingency.
Requested By Date of Request
Contractor
Connection to be made using TEK hex/washer head screws and attached to angle clips to steel framing, no welded connections included.
Description of Requested Changes 
Deletion of metal panel demolition from scope of work.
OH&P on the balance of the work outside of contingency allowance. 
Furnish and installation of metal track stud framing.
Deduct Panel Demo see  above & attached (4,590.00)$                                    
Scope  Description
Framing Modifications see  above & attached 33,728.00 $                                   
 Item Total
P.O. Box 91298, Chattanooga, TN  37412     (423) 643‐8448
Any change in Contract time required:
CHANGE ORDER REQUEST FORM
Project Name
Project #
Project Manager
Owner
Athens Public Works Renovations and Addition
11
6/7/2022
Architect/Engineer
22‐002
Rob Thew
Additional structural modifications per structural engineer comments.
6/7/2022