BASELINE

SPORTS CONSTRUCTION
www.baselinellc.com

Proposed Project Timelines

1.
2.

Option 1 — Demolition & reconstruction: 90 to 100 days
Option 2 — Crack treatment & resurfacing 14 to 21 days

Notes, Terms & Conditions:

1.
2.

oy

6.
7.
8.

Assumes construction will take place summer / fall 2023

Assumes unencumbered access to adequate material staging areas, access and haul routes and site
location for the duration of our work scope detailed above.

Pricing does not allow for the removal or replacement of unsuitable soils, unsuitable fill material, solid
rock, hazardous materials or any other items that are not suitable to support our work scope.
Assumes construction process will continue without interruption until our work scope is complete

In order to adhere to product specifications, the tennis surface must be applied in dry conditions with
ambient temperatures of at least 50-degrees and rising for a period of no less than 20 days.

Quote does not allow for work related to existing court lighting.

Quote does not allow for the repair of underground utilities.

Quote expires in 30 days

Thanks for the opportunity and please feel free to call or email if you have any questions.

Steve Clift / Vice President
M — 423.593.8284
www.baselinellc.com

ASBA CERTIFIED TENNIS COURT BUILDER ON STAFF

MEMBER

AMERICAN
SPORTS BULLDERS
ASSOCIATION

3600 Henson Road, Knoxville, TN 37921
(800) 205-9521 (865) 588-4320 fax: (865) 588-4111
Email: info@baselineLLC.com

47