PUBLIC WORKS
MEMORANDUM
TO: Deb Wallace, City Manager
FROM: Ben Burchfield, Public Works Director
DATE: August 2, 2023
SUBJECT: Stantec CTI Contract Amendment
Public Works is requesting Council approval to amend the contract for professional services with
Stantec. During the course of constructi on on the CTI project , Stantec has provided additional
redesign and construction administration services in order to amend project scope and assist in
field verification of billable quantities.
The construction task order for the project is set at $10,000.00. This number was kept low in the
hopes that minimal construction administration and redesign would happen, but that has not
been the case. Stantec has accrued an additional $22,566.25 in task s through July 26,2023 as
shown in the attached tasks budget summary beyond the approved con tract amount . These
activity costs are tied to redesign of intersection signal improvements, stormwater catch -basin
redesign based on field conflicts, and submittal/pay app review.
We are requesting Council approval to amend task number 500.1 to cover the outlined activities.
As an alternative, Council could opt to cost-shift available budget in the HDTA activities listed to
balance the costs, but staff recommends avoid doing so as we have applied for Multimodal Access
Grant (MMAG) funding for design and construction of HDTA project phase 1, which includes
pedestrian improvements at 5 -point intersection a nd adjoining streets. Assuming the City is
awarded, it is our intent to, at that time, amend and increase the HDTA contract tasks to complete
construction documents and provide construction administration for the HDTA project.
If you have any questions, please let me know.