Historical account baseline — superseded

This earlier reconciliation is not current. Its mapped/unlocated columns predate later project connections. Open current unlocated guide

Athens, Tennessee · FY2021–FY2025 · Updated September 23, 2026

Reported spending in this inventory$2,496,375.00
Estimated on the map$1,417,017.69
Still unlocated$1,079,357.31

The new local-paving connection places part of the reported spending on the map using documented street-cost proportions. These are estimated locations, not verified payment locations. Original spending totals have not changed.

Open heat map · Allocation method · Meeting-record connections

By category

CategoryReportedEstimated on mapStill unlocated
Paving$1,935,702.00$1,417,017.69$518,684.31
Stormwater$500,530.00$0.00$500,530.00
Sidewalks$60,143.00$0.00$60,143.00

Remaining paving: $436,740.31 from the FY2024–FY2025 local paving program, $68,457 in STBG expenditures, and $13,487 in FY2021 paving. STBG has a street-list connection, but is not allocated in the current model. Stormwater includes $466,200 in project expenditure and $34,330 in supplies. Sidewalks remain $60,143.

Paving documentation

Year / source accountReportedEstimated on mapStill unlocatedSource
FY2021Strip Paving$13,487.00$0.00$13,487.00Budget PDF p. 51
FY2022Strip Paving$0.00$0.00$0.00Budget PDF p. 50
FY202308-0904-6061 STBG-L Resurfacing$25,760.00$0.00$25,760.00Budget PDF p. 109
FY202401-0903-5624 Strip Paving$1,485,076.00$1,135,196.16$349,879.84Budget PDF p. 85
FY202408-0904-6061 STBG-L Resurfacing$27,832.00$0.00$27,832.00Budget PDF p. 109
FY202501-0903-5624 Strip Paving$368,682.00$281,821.53$86,860.47Budget PDF p. 86
FY202508-0904-6061 STBG-L Resurfacing$14,865.00$0.00$14,865.00Budget PDF p. 114

Stormwater documentation

Year / source accountReportedEstimated on mapStill unlocatedSource
FY2021Storm Water Supplies$7,392.00$0.00$7,392.00Budget PDF p. 51
FY2022Storm Water Supplies$0.00$0.00$0.00Budget PDF p. 50
FY202301-0903-5366 Storm Water Supplies$10,566.00$0.00$10,566.00Budget PDF p. 85
FY202308-0901-6109 Storm Water Project$38,105.00$0.00$38,105.00Budget PDF p. 109
FY202401-0903-5366 Storm Water Supplies$15,865.00$0.00$15,865.00Budget PDF p. 85
FY202408-0901-6109 Storm Water Project$87,775.00$0.00$87,775.00Budget PDF p. 109
FY202501-0903-5366 Storm Water Supplies$507.00$0.00$507.00Budget PDF p. 86
FY202508-0901-6109 Storm Water Project$340,320.00$0.00$340,320.00Budget PDF p. 114

Sidewalks documentation

Year / source accountReportedEstimated on mapStill unlocatedSource
FY2021Sidewalk Projects$19,119.00$0.00$19,119.00Budget PDF p. 52
FY2022Sidewalk Projects$0.00$0.00$0.00Budget PDF p. 51
FY202301-0904-6030 Sidewalk Maintenance$33,241.00$0.00$33,241.00Budget PDF p. 83
FY202401-0904-6030 Sidewalk Maintenance$7,783.00$0.00$7,783.00Budget PDF p. 83

Scope

This is a partial inventory. Park-associated amounts are separate. Missing values and printed dashes are excluded; explicit zeros are retained. Estimates, awards and grants are not added to reported expenditures. Annual estimated allocations use the same street proportions and do not establish the year each street was worked on. Dollar cents preserve reconciliation; they do not imply precise geographic knowledge.

Source links use physical PDF pages and retained City URLs; remote availability was not rechecked for this update.